KAZ Minerals bumps up Baimskaya budget and coronavirus delays BFS

Drilling has indicated a potential increase in mineral resources that would lead to an extension of the mine life from the previous guidance of around 25 years

KAZ Minerals PLC (LON:KAZ) said the estimated capital budget for the Baimskaya copper project in Russia has increased to around US$7bn over the seven years of construction.

Recent delays will mean the bankable feasibility study for the project is now expected to be completed by the end of December, having expected to be completed before the end of the first half of the year, while capex guidance for 2020 remains at US$150mln.

The FTSE 250 group acquired Baimskaya, one of the world's top ten undeveloped copper deposits, for US$900mln in January last year, estimating capex of US$5.5bn at that time.

Drilling, although it has been halted by coronavirus restrictions, has indicated a potential increase in mineral resources that would lead to an extension of the mine life from the previous guidance of around 25 years.

As a result, management is looking to step up design capacity for the mineral concentrator from 60mln tonnes per annum (Mtpa) of ore processed to 70 Mtpa.

KAZ said it now plans to ramp up the processing plant’s two lines in consecutive phases around 12 to 18 months apart, which it said will reduce the peak funding requirement compared to the previous aim for simultaneous startup.

Shares in the company fell 10% to 445.5p on Friday morning.

Analysts at broker Liberum said: "We expect also the delay has to do with low copper prices and that they are unlikely to find anyone to share the project risk in this type of commodities environment."

They added: "These capacity expansions mid-design usually mean that the project economics don't stack up on a smaller scale, as for the need to spread the infrastructure costs etc, it also masks the capex intensity increase of 9% to $20,800 per tonne of copper equivalent capacity. In comparison Taseko's Florence project capex intensity is $5,263/t.

"It is difficult to see how KAZ Minerals walks away from the project that is loathed by investors but we expect they will continue to delay until market conditions are more in their favour."