Rambler Metals and Mining (LON:RMM, CVE:RAB) is now ‘financially positioned’ to start pre-production development work at the Ming mine while it continues the Nugget Pond mill expansion, said chief executive George Ogilvie.
This morning the group released its third quarter results. In the three months ended 31 January 2011 Rambler made a net loss of $555,000, or $0.006 a share.
Importantly it recently increased cash resources to $7.6 million by 21 March 2011, compared with $4.9 million at the end of January. This was thanks to the final US$6 million funding from Sandstorm, after it got the construction approval for the mine - which happened after the reporting period.
"We are extremely pleased with the progress made over the past quarter in developing the Ming Copper-Gold Mine as well as the renewed exploration program,” Ogilvie said.
“Following receipt of complete construction approval from the provincial authorities Rambler is now financially positioned to begin pre-production development in the mine whilst continuing work on the Nugget Pond Mill expansion.
He adds: “Supported with high copper and gold prices and strong fundamentals we aim to further advance both the Nugget Pond Crown Pillar and the Tilt Cove East Mine projects into production during 2011.”
Operationally Rambler completed a number of milestones. It submitted environmental registration for the mining of the Nugget Pond’s Crown Pillar deposit, which is slated to start in the next three months (the second calendar quarter of 2011).
It got approvals to build its office and dry facilities at the Ming Mine, as well as its fresh water source. Importantly these permits triggered a US$7 million drawdown from Sandstorm Gold. Later – post period – it got the final construction approvals and it received the final US$6 million payment.
It also agreed net smelter royalty (NSR) terms with Metals Creek Resources (MEK) to process material from the Tilt Cove East Mine – about 23 kilometres away from the Nugget Pond Mill.
Rambler said that the Nugget Pond expansion programme continues ‘at pace and on schedule’. It has also restarted exploring the Ming Mine.