London Mining (LON:LOND) reported on an eventful fourth quarter and full year to December 31 2010, saying it continued to deliver on key milestones throughout 2010, progressing its plans to produce over 30 million tonnes per annum (Mtpa) of iron ore by 2015.
The Marampa project in Sierra Leone will produce its first iron ore in Q3 of this year as it begins development to its 16 Mtpa target and first coke will be also produced from the Socha project in Colombia in Q3 2011.
At Isua in Greenland, the company has increased the scope of the project to 15 Mtpa which is scheduled to commence production in early 2015 and it is progressing funding of the project.
Chief executive Graeme Hossie said: “The continued rapid progress towards substantial production from our projects validates our strategy of focusing on ore bodies which will produce high quality product at low operating cost, with simple and deliverable logistics and which can be developed rapidly into sizeable and scalable production."
At the end of January, London Mining raised US$110 million through an offering of senior, unsecured convertible bonds due 2016 to certain international institutional investors to primarily fund Phase 1 capital expenditure for Marampa.
The month also saw the receipt of the final environmental permit required for the project and an offtake agreement with trading house Glencore International AG for the initial production.
At Isua, the recently completed scoping study will form part of the bankable feasibility study, which is expected to be finished by the end of this year.
London Mining is now constructing coke ovens with a capacity of 200,000 tonnes per annum in the Boyaca region of Colombia. Completion of construction and first coke production is now expected in Q3 2011. Full capacity is expected to be reached in Q1 2012, following which the company expects to commence a second phase of construction, increasing capacity to 400ktpa of coke.