Bright news from Millennial Lithium Corp (CVE:ML) on Monday, which announced it had positive drilling and analytical results from the latest exploration wells at its Pastos Grandes project in Salta, Argentina.
Shares of the company soared, up 19.1% at C$1.81.
The company said two new exploration holes have intersected, and bottomed in, lithium-bearing brine zones, with one hole intersecting positive lithium grades in a 545-metre-thick lithium-bearing horizon, including a high grade of 701 milligrams per litre lithium.
The company said a 40-person camp is being put in at the site, including a state-of-the-art solar-hybrid power system, as work advances at the site on a pilot plant to produce battery-grade lithium carbonate.
WATCH: Millennial Lithium drills south of their flagship project and receives good results
"We are very encouraged to see that drilling on the REMSA licence at Pastos Grandes salar continues to encounter lithium-rich brine, significantly extending the area of known lithium-rich brine further west toward the edge of the salar. Millennial has already started a full feasibility study on its lithium brine project in Pastos Grandes, Salta, which is scheduled to be completed in Q2 2019," said chief executive officer Farhad Abasov.
"Millennial is fully funded to complete the feasibility study as well as all other programs with a very strong cash balance of $56-million. The company is embarking on a process of securing construction financing, which is planned to be concluded in 2019."
The company said two exploration holes were drilled to depths of 641 metres and 605 metres, respectively, and both wells terminated in brine-bearing sand.
According to the firm, these holes confirm the extension of the brine on to the contiguous REMSA licence southeast and southwest of the original core Pastos Grandes licences suggesting additional potential to expand the currently calculated resource beyond the initial Pastos Grandes licences, according to the firm.
The company said exploration drilling is continuing with a rig currently at one of the holes, located in the southwest corner of the REMSA licence.
Drilling is currently at a depth of 389 metres and a second drilling machine is mobilizing to another hole.
The company said in addition, the 21-day pumping test has been completed and data compilation is underway.
Two pumping well drill machines have been mobilized to site to expedite additional pumping tests.
The company said pilot evaporation ponds, approximately 3.25 hectares in size, have now been filled with brine to provide concentrated lithium plant-grade feed for the company's pilot plant.
Contact Katie Lewis at katie@proactiveinvestors.com
Follow her on Twitter: @kelewis