SDX Energy Inc (LON:SDX) told investors it has spudded its latest well at the Sebou project in Morocco.
The KSR-16 well is expected to be drilled in 20-25 days, and it is earmarked as a production well.
READ: SDX Energy is now seeing the financial benefits of the Circle Oil acquisition
Flow testing and the hook up to production facilities is expected to take a further 21 days following the drill programme.
It is the third of a nine planned wells across the company’s Morocco portfolio which comprises the Sebou, Gharb Centre and Lalla Mimouna permits.
WATCH: SDX Energy's KSR-14 well alone sufficient to meet local demand, says CEO Paul Welch
SDX also confirmed that the recently drilled KSR-15 well is currently being connected to the production infrastructure, and it is expected to be placed on test production within the next 10 days.