Iron Road (ASX: IRD) has reported that a significant exploratory drilling programme at the company’s wholly owned Central Eyre Iron Project (CEIP) in South Australia has been approved by Primary Industries and Resources South Australia (PIRSA).
It is the second of several drilling programmes planned by Iron Road at CEIP during 2010 and is planned to commence on 07 June 2010. The drilling comprises 42 holes for 9,845m.
The company said the programme is planned to define the potential of seven high priority targets across Warramboo, Kopi and Hambidge project areas on EL3699. These have been selected based on geophysical as well as historical data.
Iron Road Managing Director, Andrew Stocks, said that the programme continued the significant amount of project development work underway at Iron Road.
“This is now our second drilling programme for the year and very much indicates our intention to rapidly develop the Central Eyre Iron Project."
"Iron Road has set out a pathway during 2010 to achieve a substantial amount of progress, including the delivery early in 2011 of a pre-feasibility study,” said Stocks.
The drilling programme will be undertaken by Gomex Drilling for the RC component and Coughlan Drilling for the diamond drilling component.
Iron Road said the programme will utilise one RC drill rig and two diamond drill rigs. Since the programme is designed to be scalable (new programmes are subject to PIRSA approval) a third diamond drill rig has already been secured.
Stocks said "when appropriate, diamond drilling may move to a double shift basis to accelerate progress further."
"The drilling programme forms part of a planned strategy to establish a long-life +10Mtpa magnetite concentrate export operation," he added.
Test work from the Stage I and II drilling programmes indicates that a high quality concentrate may be produced from the Warramboo project area grading ~70% iron with low impurities.
In addition, metallurgical test work indicates excellent beneficiation characteristics with good potential for optimisation leading to a reduction in operating costs.
Iron Road said its corporate objectives include increasing the mineral resource across the Central Eyre Iron Project to 500Mt in 2010.